Our Design

West Seattle · Microcement

A continuous microcement shower.

Completed

West Seattle microcement bathroom — Blender rendering
Opening the 3D model…
More views

Reconstructed from project records · Approximate dimensions

Drag to turn · Scroll or pinch to zoom · Arrow keys to rotate

About this view

The continuous floor links the shower, toilet and refinished vanity opposite the frosted window.

The article and opposite-facing photos establish the fixture grouping, oak-framed mirror and warm continuous finish. Room length, threshold, joinery and window position are estimated.

The tub in this West Seattle rental had already been reglazed once. When the coating started to fail, the owner had a choice to make about the next tenant's bathroom. He asked us for a walk-in shower with fewer joints to clean and a finish worth carrying through the rest of the room.

Compare model and photo

Read the project story

From the model to the build

A continuous finish around the shower

The team carried the hand-applied microcement from the walls onto the sloped pan. That left the edge of the glass and the dark shower fittings as the main lines in the room.

Eye-level reconstruction looking into the warm microcement shower, with a fixed glass screen, dark square head and wall control.
Blender reconstruction
Completed West Seattle shower seen past the frosted window, with warm microcement, a dark shower head and a single glass panel.
Project photograph

The doorway photo shows the wooden corner stand to the left of the shower. The opposite view shows the square black mixer beneath the rain head and the dark rectangular drain in the continuous floor.

Explore this space at eye level
Open this comparison in 3D

Project team

Who designed and built it

The owner set the brief for a durable rental bathroom. DuetRight built the shower and carried the material and wood details through the room.

Following the old shower door

The before photograph shows why the tub enclosure was awkward to live with. A tall tub wall and a sliding glass door occupied the same narrow opening. The metal track collected grime. Inside, a change from tile to tub added another joint to look after. The owner wanted to simplify what a tenant would use every day and what he would have to maintain between tenancies.

A fixed piece of glass could take the place of the slider. Microcement would let us finish the wall, pan and bathroom floor in the same warm tone. Taking those two decisions together removed the overhead door track and let the floor run visually into the shower.

Original tub-shower combo with sliding glass door and white tile surround before microcement conversion in West Seattle.
The original tub-shower combo

Building the pan below the finish

The old tub and its surround came out to the studs. In their place we built a sloped mortar-bed pan with a PVC liner and waterproofed the shower. We held water in the pan for 24 hours before applying the finish. The photograph of the crew working on the pan records the part of this room that disappeared under the microcement.

We hand-applied two coats to the shower walls, then carried the finish across the pan and onto the main floor. Once it cured, we sealed it with a matte polyurethane topcoat. A fixed frameless panel went in after the plumbing and valve trim were fitted and tested.

Stan waterproofing the shower pan and cement board walls during tub-to-shower conversion in West Seattle.
Working the shower pan and waterproofing

Keeping the mirror and the counter

Across from the shower sat a vanity that could still serve the room. We surfaced the existing counter in a matching tone, changed the pulls and fitted a low-profile matte black faucet. A black light above the mirror repeats that finish.

The existing mirror stayed. We built a frame for it in oak. In the completed vanity photograph, the oak frame echoes the cabinets, and the pale counter carries the shower finish across the room. Reusing the mirror and counter also kept two serviceable pieces out of the demolition pile.

Refreshed bathroom vanity with light oak cabinet, microcement countertop, matte black hardware, and updated vanity light fixture.
The new and improved vanity space

What a tenant sees at the door

The new sightline goes to a rain head and a single pane of clear glass. Below it, the sloped shower floor and the surrounding floor read as one surface. The finished photographs show that continuity in daylight and under the vanity light. The owner gained a bathroom with fewer edges and tracks to clean, along with the open shower he wanted to offer his tenants.

Finished West Seattle walk-in shower with a fixed glass screen, a dark square rain head and warm microcement walls.
The finished bathroom

Before & after

See what changed.

Move the divider to compare the two photographs.

Microcement tub-to-shower before renovationMicrocement tub-to-shower after renovation
BeforeAfter
Microcement tub-to-showerOriginals BeforeAfter

Blender detail study

Continuous finish at the shower corner.

Continuous finish at the shower corner — rendered material detail
Reconstruction from project records · November 2026

A closer look in motion

Five-second Blender camera study · Continuous finish at the shower corner

From the site

The project in photographs.

Project record